Question:

In a hydroelectric plant the available head is 80 m for a

Last updated: 6/9/2023

In a hydroelectric plant the available head is 80 m for a

In a hydroelectric plant the available head is 80 m for a discharge 12m sec and overall efficiency of the Power Station of 80 The specific weight of water is 9 81 k m2 Then the power developed is in MW