Question:

Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G

Last updated: 9/18/2023

Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G

Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G H Figure 7 6 Network Scheduling Data Duration days 5 20 15 in 5 60 050 15 20 15 2 Consider the network scheduling data presented in Figure 7 6 How many days of slack are associated with activity E a 0 b 107