Question:

Activity Node A 1 B 1 C 2 D 3 Start Finish Node 2 3 4 4

Last updated: 1/12/2024

Activity Node A 1 B 1 C 2 D 3 Start Finish Node 2 3 4 4

Activity Node A 1 B 1 C 2 D 3 Start Finish Node 2 3 4 4 Multiple Choice O What is the estimated expected mean time for activity D O 32 days 42 days 40 days Optimistic 41 54 58 32 41 days Duration days Most Likely 50 60 70 41 Pessimistic 59 66 82 44