Question:
On-Time Delivery Company acquired an adjacent lot to
Last updated: 8/11/2022
On-Time Delivery Company acquired an adjacent lot to construct a new warehouse, paying $34,000 in cash and giving a short-term note for $281,000. Legal fees paid were $1,590, delinquent taxes assumed were $13,800, and fees paid to remove an old building from the land were $21,400. Materials salvaged from the demolition of the building were sold for $4,700. A contractor was paid $957,600 to construct a new warehouse. Determine the cost of the land to be reported on the balance sheet. $