Question:

Prepare a master production schedule for industrial pumps in

Last updated: 1/9/2024

Prepare a master production schedule for industrial pumps in

Prepare a master production schedule for industrial pumps in the manner of the following table Use the MPS rule to schedule production when the projected on hand inventory would be less than 10 without production Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used Leave no cells blank be certain to enter 0 wherever required Forecast Customer orders committed Projected on hand inventory MPS ATP 30 33 2 June 30 20 3 30 10 4 30 4 5 40 2 6 July 40 7 40 8 40