Question:
The network diagram and task times for a project are shown
Last updated: 5/18/2023

The network diagram and task times for a project are shown below A Task A1 A2 A3 A4 A5 A 2 A3 Duration days 7 1 4 4 7 A4 What is the early finish time for activity A5 A days