Question:

Two companies working together can clear a parcel of land in

Last updated: 10/12/2023

Two companies working together can clear a parcel of land in

Two companies working together can clear a parcel of land in 30 hours Working alone it would take Company A 3 hours longer to clear the land than it would Company B How long would it take Company B to clear the parcel of land alone Round your answer to the nearest tenth