Question:
Question 1 25 points Using the following information to
Last updated: 5/3/2023

Question 1 25 points Using the following information to create an EST graph one is set up for you Which of the below is the correct critical path and minimum project time Start 0 0 5 B 0 0 5 D 1 0 3 0 BCEHIJK 51 7 BCDEFGIJK 51 7 ACDEHIJK 51 7 ACDEFGIJK 51 7 36 E 4 0 36 F 3 5 G 40 H 1 5 40 43 5 1 2 K 49 2 3 5 I 1 0 J 44 7 45 7 2 5 FINISH 51 7