1 Cars arrive at a one bay car wash facility where the

Last updated: 7/13/2023

1 Cars arrive at a one bay car wash facility where the

1 Cars arrive at a one bay car wash facility where the interarrival time is exponential with mean of 10 minutes Arriving cars line up in a single line It takes between 10 and 15 minutes uniformly distributed to wash a car Assume first arrival occurs at time 0 T 0 and system is empty initially Simulate the system for first 7 customers and calculate the following performance measures a What is the average queue length 20p b What is server utilization 20p c What is the average time that a customer waits in the queue 20p X Ln R Table 1 Random numbers x 9 a 6 a R Random Numbers for Interarrival times Random Numbers for Service times 0 3397 0 1351 0 2677 0 8762 0 9912 0 8176 0 2236 0 8422 0 8820 0 8471 0 4249 0 9113 0 9387 0 3456 2 Using multiplicative congruential method generate 10 random numbers for following input parameters 20p