Question:
2 In constructing a new road the design estimates the
Last updated: 11/8/2023
2 In constructing a new road the design estimates the following areas for earthwork by the stations provided 6 points STA Area ft 119 00 0 120 00 120 121 00 224 122 00 325 123 00 450 124 00 362 125 00 0 The cost for extracting the soil is 20 per cubic yd and moving the soil is 5 per cubic yd Determine the total cost to extract and move the estimated volume of earth