3 A work task has a current cost of 6 000 with a budget cost

Last updated: 2/5/2024

3 A work task has a current cost of 6 000 with a budget cost

3 A work task has a current cost of 6 000 with a budget cost at this same point of 4 000 The total budget or this task is 9 000 The estimated cost at completion for this task is most nearly