4 What is the minimum time Critical path that the project
Last updated: 2/5/2024
![4 What is the minimum time Critical path that the project](https://media.kunduz.com/media/sug-question-candidate/20240205002554192274-4566921.jpg?h=512)
4 What is the minimum time Critical path that the project can be completed by for the following CPM network diagram A 4 days 3 days B 8 days D 4 days Professor Dr M G Attara PE PhD E 9 days 6 days G 7 days