Question:

A company is ordering material from its supplier They need

Last updated: 5/23/2023

A company is ordering material from its supplier They need

A company is ordering material from its supplier They need two types of parts called Part A and Part B Part A costs 8 each while Part B costs 2 each For Part A they already have 15 of them but in total they need 5 parts for each of 7 jobs For Part B they currently have 6 of them but in total they need 4 parts for each of 3 jobs How much will it cost them to buy everything they need to order