Question:

A contractor builds two models of homes model A and model B

Last updated: 11/28/2023

A contractor builds two models of homes model A and model B

A contractor builds two models of homes model A and model B Model A requires 200 worker days of labor and 240 000 in capital and model B requires 500 worker days of labor and 300 000 in capital The contractor has a total of 5000 worker days and 3 600 000 in capital available per month The profit is 60 000 on model A and 75 000 on model B Building how many of each model will maximize the monthly profit What is the maximum possible profit Building how many of each model will maximize the monthly profit Profit is maximized with 15 models A homes and or with 10 model A homes and model B homes model B homes with model A homes and 8 model B homes