Question:

A firm uses a serial assembly system and needs answers to

Last updated: 9/20/2023

A firm uses a serial assembly system and needs answers to

A firm uses a serial assembly system and needs answers to the following a An output of 880 units per shift 8 00 hours is desired for a new processing system The system requires product to pass through four stations where the work content at each station is 32 seconds What is the required cycle time for such a system Round your answer to the nearest whole number Cycle time seconds b How efficient is your system with the cycle time you calculated Round your answer to 1 decimal place Efficiency c Station 3 changes and now requires 50 seconds to complete What will need to be done to meet demand assume only 8 00 hours are available What is the efficiency of the new system Round your answer to 1 decimal place To satisfy the demand station 3 will and the efficiency is 98