Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G
Last updated: 9/18/2023
![Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G](https://media.kunduz.com/media/sug-question-candidate/20230918005123067148-5941188.jpg?h=512)
Activity A B C D E F G H 1 Predecessor s A A A B C D E E F G H Figure 7 6 Network Scheduling Data Duration days 5 20 15 in 5 60 050 15 20 15 2 Consider the network scheduling data presented in Figure 7 6 How many days of slack are associated with activity E a 0 b 107