The county administrator's office is making plans to finance
Last updated: 7/15/2022
The county administrator's office is making plans to finance the next phase of infrastructure repair to the county's roads and bridges. To help with their planning, they have developed functions that model the anticipated tax money available and planned budget for repairs, for any given year, x years from today. The expected tax money, in millions, received from the state is represented by the function 7(x) = 14x³ + 43x² + 37x+ 190. The planned budget allocating money, in millions, for infrastructure repairs in that same year is represented by the function R(x) 35x +90. Which function represents the balance, in millions, that remains in a given year, after using a portion of the tax money to pay for infrastructure repairs? DA. B(x) = 14x³ + 8x² + 37x+100 OB. B(x) = 14x³ + 8x² +37x+ 280 OC. B(x) = 14x³ + 43x² + 2x + 100 OD. B(x) = 14x³ + 43x²+2x+280