Question:

The desired daily output for an assembly line is 480 units

Last updated: 9/20/2023

The desired daily output for an assembly line is 480 units

The desired daily output for an assembly line is 480 units This assembly line will operate 640 minutes per day The following table contains information on this product s task times and precedence relationships TASK time ABCDEFGH Workstation cycle TASK TIME SECONDS 40 25 75 15 59 Work Station 30 25 15 IMMEDIATE PREDECESSOR b What is the workstation cycle time 3x Task A B B Answer is complete but not entirely correct seconds per unit D C E G F c Balance this line using the largest number of following tasks Use the longest task time as a secondary criterion Leave no cell blank be certain to enter 0 wherever required Idle Time