Question:

The following bar chart shows the activities to complete a

Last updated: 5/22/2023

The following bar chart shows the activities to complete a

The following bar chart shows the activities to complete a project in 6 months each column represents 1 month The total project cost is 1 480 Activity ABC D E F G H I J Cost 100 200 60 80 40 150 300 100 50 400 Month Month 1 2 Month Month Month 3 4 5 Month 6 After 3 months Activities A B C E and half of F were completed for a cost of 490 What is the status of this project in terms of the schedule and budget Conduct the earned value analysis EVA variance analysis and trend analysis for this project and discuss the result of your analysis