The following table contains order dependent setup times for

Last updated: 1/12/2024

The following table contains order dependent setup times for

The following table contains order dependent setup times for three jobs Following Job s Setup Time hrs A Preceding Job B C Setup Time hrs 2 4 3 2 2 0 A Al B C 1 8 2 2 1 4 0 8 2 6 1 3 Click here for the Excel Data File Which processing sequence will minimize the total setup time