Question:

The operations manager of a large production plant would

Last updated: 7/12/2022

The operations manager of a large production plant would

The operations manager of a large production plant would like to estimate the average amount of time workers take to assemble a new electronic component. After observing a number of workers assembling similar devices, she guesses that the standard deviation is 7 minutes. How large a sample of workers should she take if she wishes to estimate the mean assembly time to within 20 seconds. Assume the confidence level to be 99%. Sample Size =