The order planning a project is O Collect requirements

Last updated: 3/18/2023

The order planning a project is O Collect requirements

The order planning a project is O Collect requirements Identify scope Identify sequence activities Create budget b Identify scope Collect requirements Create schedule c Create budget Create schedule Fit scope into the schedule a d Establish scope Collect requirements Create Schedule Create budget