Question:
The various paths are 1 2 3 Job 1 2 The critical path is 1 2
Last updated: 10/10/2023
The various paths are 1 2 3 Job 1 2 The critical path is 1 2 3 5 8 and 1 6 7 8 The project duration is 36 days Variance of the critical path 4 16 16 36 Exercises 1 A project consists of 12 jobs Draw a project network and determine the critical path 2 3 2 4 3 4 3 5 4 6 5 8 Activity 1 2 1 3 3 5 3 4 4 6 5 6 6 7 6 8 7 8 8 9 Duration 2 7 3 3 5 3 5 1 2 4 5 8 1 2 3 5 8 1 6 7 8 2 Consider the following project whose activities along with PERT time estimates the optimistic time a most likely time m and the pessimistic time b are given as follows a days 12 7 4 36 12 6 9 6 4 8 Job 6 7 75 6 10 7 9 8 9 9 10 m days 14 10 6 Duration 23 36 36 40 15 8 12 10 5 10 Duration 8 4 4 1 7 b days 21 16 10 60 24 12 18 15 7 14