Question:
Which combination of True and False is correct? 1) In making
Last updated: 8/8/2022
Which combination of True and False is correct? 1) In making a forward pass through a network, three activities are immediate predecessors for activity T. The early start time for activity T is the largest EF for the three activities that are immediate predecessors for activity T. 2) In critical path scheduling, slack is computed as the difference between finish and start times. Select one: a. 1) True and 2) True b. 1) False and 2) False c) True and 2) False d 1) False and 2) True